GENERATOR > INSTALLATION

for Preparation Click here



1. INSTALL GENERATOR ASSEMBLY


A112761
  1. Install the generator and adjusting bar with the 2 bolts.

    Torque:
    43 N*m{ 438 kgf*cm , 32 ft.*lbf }

  1. Install the generator wire with the nut.

    Torque:
    9.8 N*m{ 100 kgf*cm , 87 in.*lbf }

  1. Connect the generator connector.



2. INSTALL DRIVE BELT


3. INSTALL V-BANK COVER


A076442E01
  1. While turning the belt tensioner counterclockwise, align its holes, and then insert a bar of 6 mm (0.24 in.) into the holes to fix the belt tensioner.

  1. Install the V-ribbed belt.

  1. While turning the belt tensioner counterclockwise, remove the bar.



    A113028E02
  1. If it is hard to install the V-ribbed belt, perform the following procedure.

    1. Put the V-ribbed belt on everything except the P/S pump as shown in the illustration.

    2. While releasing the belt tension by turning the belt tensioner counterclockwise, put the V-ribbed belt on the P/S pump.



4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL


5. PERFORM INITIALIZATION
  1. Perform initialization (Click here).

    NOTICE:
    Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.