A/T Shift Solenoid Valve Test

  1. Disconnect the shift solenoid wire harness connector.
  1. Measure the resistance:
    • No. 1 terminal: Shift solenoid valve C
    • No. 2 terminal: Shift solenoid valve B
    • No. 3 terminal: Shift solenoid valve E
    • No. 5 terminal: Shift solenoid valve A
    • No. 8 terminal: Shift solenoid valve D
    Standard:
    12−25 Ω

    • If the resistance is within the standard, go to Step 9 .
    • If the resistance is out of standard, go to Step 10 .
  1. Connect a jumper wire from the negative battery terminal to body ground, and connect another jumper wire from the positive battery terminal to each shift solenoid wire harness connector terminal individually. A clicking sound should be heard.
    • If a clicking sound is heard, the valves are OK. The test is complete, reconnect the connector, and install all removed parts.
    • If no clicking sound is heard, go to Step 10 .